What you may receive
- Disruption and prolongation merits review
- Constraint and cause-and-effect register
- Period and activity mapping
- Productivity-analysis briefing
- Integrated time-and-cost narrative
- Claim, response or independent report
Delay, disruption and prolongation are connected but different. Constructive Advisory helps clients distinguish the time impact on completion from productivity loss and time-related cost, then structure the evidence needed to support or test each part of the case.
Constructive Advisory provides independent construction claims, delay, programme and dispute support from Singapore for matters across Asia-Pacific and other international regions.
The work is coordinated with quantum, commercial and legal advisers where necessary so that the technical case remains consistent without overstating what programme analysis alone can prove.
The final deliverables and information request are adjusted to the dispute stage, materiality, available records and agreed programme.
Define which alleged effects concern completion delay, productivity disruption, prolongation cost or another head of loss.
Assess whether the available records support measured-mile, earned-value, programme-based or other forms of analysis.
Connect the alleged events to the affected work, periods, resources and consequences while accounting for competing causes.
Align the technical findings with the contractual and quantum analyses without crossing professional boundaries.
No. Delay generally concerns time impact, often to a milestone or completion. Disruption concerns loss of productivity or efficiency. A project may suffer one, both or neither, and each requires its own evidence and analysis.
Contemporaneous labour, plant, output, location, progress, instruction, access and daily records are especially valuable. The data must allow affected and unaffected work or periods to be compared reliably.
Not automatically. The relevant contract, compensable cause, concurrency, mitigation and actual cost evidence must be considered. Time entitlement and cost entitlement may differ.
Constructive Advisory focuses on delay, programme, causation and claim strategy. Quantum work can be coordinated with an appropriate quantity-surveying or damages specialist where required.
Share a brief outline of the project, claim or dispute. Initial enquiries are treated in confidence and remain subject to conflict and engagement checks.